HGV charging infrastructure specialists

HGV Electric Vehicle Charging Infrastructure

From 1MW depot chargers to 20MW public hubs. We deliver the full electrical infrastructure package for HGV EV charging, from POC application to operational handover.

HV specialist EMS expertise Principal contractor
The Process
1
Load assessment & POC strategy
2
Substation & HV design
3
Cable & civil installation
4
EMS, BESS & commissioning
From POC to Operational Hub

The Process Step by Step

Every HGV charging infrastructure project follows a structured delivery sequence. Here is exactly what we do at each stage.

1

The Scale of the Challenge

HGV electric vehicle charging operates at a fundamentally different scale to car charging. Each HGV bay requires 100 to 400kW. A depot with 10 vehicles charging simultaneously needs 1.5 to 3.5MW of power. A public HGV charging hub with 20 bays may need 4 to 8MW. At this scale, a simple LV connection is not possible. An 11kV or 33kV grid connection, on-site substation infrastructure, and intelligent energy management are all required. USP has delivered HGV charging infrastructure at this scale, including the Voltempo hub at Felixstowe.

2

POC Strategy

Above approximately 1MW, the DNO treats the connection as a bespoke connection. Lead times are typically 18 to 36 months. For a site targeting operation in 2026, the POC application needs to be submitted now. USP develops a POC strategy that identifies the most deliverable connection point, assesses whether 11kV or 33kV is required, and identifies what can be progressed in parallel (BESS selection, substation design, civil works) to reduce the critical path. We submit the application and manage the NGED connection process.

3

Energy Management and Smart Charging

Unmanaged charging is not viable at HGV scale. If 10 HGVs all plug in and charge at full power simultaneously, the peak demand exceeds what most grid connections can economically deliver. An energy management system (EMS) allocates available power dynamically between active chargers, prioritising vehicles with lower state of charge or earlier departure times. Overnight and off-peak staggering further reduces peak demand. USP advises on EMS selection and integration with charger management systems.

4

Battery Energy Storage

A battery energy storage system (BESS) is a highly effective tool for managing peak demand at HGV charging hubs. The BESS charges from the grid during off-peak periods, typically overnight, when electricity is cheapest and network demand is low. During peak charging periods it discharges, reducing the import from the grid and therefore the Maximum Import Capacity contracted with the DNO. This can reduce both connection costs and ongoing network charges. USP assists with BESS sizing, supplier selection, and integration with the EMS.

EV charging infrastructure installation
Proof on the Ground

See it in action

USP delivered the electrical infrastructure for the Voltempo HGV charging hub at Felixstowe. From POC application to operational handover, under one contract.

1MW+
HGV hub delivered
50
5-star Google reviews
10+
Industry accreditations
Key Technical Considerations

Technical Specifications

The critical parameters that govern every HGV EV charging infrastructure project.

Charger power
100 to 400kW per HGV bay. Compare with 7 to 22kW for domestic EV charging.
Connection voltage
Above approximately 1MW: 11kV HV connection required. Above approximately 5MW: 33kV connection may be required.
Substation
1,000 to 2,000kVA per substation. Multiple substations for larger hubs. GRP ground-mounted enclosures standard.
POC lead time
18 to 36 months for bespoke HV connections. Apply now for 2026 and 2027 operation targets.
EMS
Energy management system essential for managing peak demand within Maximum Import Capacity. Integration with charger management required.
BESS
Battery energy storage reduces peak import from grid, enabling off-peak charging and reducing connection and network costs.
Why Choose USP

What USP Can Do For You

Complete HGV charging infrastructure delivery from a single provider with proven experience.

Direct HGV charging experience including the Voltempo Felixstowe 1MW+ hub, providing proven capability at this scale.
Full HV connection process management from POC application through to NGED adoption, with active lead time management.
EMS selection support and BESS integration advice, modelling the economics of storage versus larger connection capacity.
CDM capability and Construction Phase Plan responsibility as Principal Contractor for larger HGV charging infrastructure projects.
Combined electrical design, civil delivery, and project management capability as a single delivery point for the complete infrastructure package.
Certified Provider

Fully Accredited & Committed to Safety

Every HGV charging project we deliver meets the highest industry standards. Worker safety, public safety, environmental responsibility, and project compliance from planning to sign-off.

WaterSafe accredited
WIAPS accredited
LRQA WIRS certified
LRQA NERS certified
LRQA GIRS certified
ISO 9001 certified
Achilles UVDB Silver Plus
Constructionline member
SSIP accredited
Acclaim accredited
What Our Clients Say About Us

Rated 5.0 ★★★★★

50 Google Reviews

HGV EV Charging FAQs

Frequently Asked Questions

HGV chargers typically require 100 to 400kW per bay. A depot with 10 vehicles operating simultaneously could need 1.5 to 3.5MW of power. This is an order of magnitude higher than a car charging hub, and requires a fundamentally different approach to connection design. At this scale, 11kV HV connections, on-site substations, and energy management systems are not optional, they are essential.
For HGV charging above approximately 1MW, the connection is treated as a bespoke connection by the DNO. Lead times for bespoke HV connections are typically 18 to 36 months from application to energisation, depending on network constraints, reinforcement requirements, and wayleave and planning processes. For sites targeting operation in 2026 or 2027, the POC application should be submitted now. USP can advise on the application strategy and what can be done in parallel to reduce overall lead time.
Yes, in many cases significantly. A battery energy storage system (BESS) charges from the grid at off-peak times when electricity is cheaper, and discharges during peak charging periods. This reduces the Maximum Import Capacity (MIC) required from the DNO, which can reduce both connection costs and ongoing network charges. For large HGV hubs, the economics of BESS versus a larger grid connection need to be modelled carefully. USP can assist with the modelling and BESS selection.
Yes. USP holds the CDM capability and carries Construction Phase Plan responsibility as Principal Contractor on HGV charging infrastructure projects. This is particularly relevant for larger hubs where multiple subcontractors are working simultaneously on civil, electrical, and technology elements. Acting as Principal Contractor gives clients a single point of accountability for health, safety, and programme on site.
For very large HGV charging hubs above approximately 5MW, a 33kV connection may be required. This involves significantly longer lead times, more complex engineering, and potentially National Grid involvement depending on network topology. USP can advise on the connection strategy for large-scale hubs and identify whether 11kV or 33kV is appropriate for your site. For 33kV connections, USP works with specialist HV engineers as part of a managed design team.
Get Started

Planning an HGV
Charging Installation?

Tell us about your project and we will advise on connection strategy, lead times, and BESS options within 24 hours.

100% free, no obligation Response within 24 hours 5.0 from 50 Google reviews

Prefer to talk? Call 024 7542 6505 for immediate service.

Get a Quote