NERS accredited EV infrastructure specialists

EV Charging Connections for Residential Developments

Part S compliant EV charging infrastructure designed in from the outset. Grid connections, feeder pillars, passive ducting, and smart charging for developments of all scales.

NERS accredited Part S compliant Smart charging
The Process
1
Load assessment with EV diversity
2
Grid connection application & design
3
Distribution, feeder pillars & ducting
4
Charger supply & commissioning
From Planning Condition to Live Charging

The Process Step by Step

Every residential EV charging project follows a clear sequence. Here is exactly what happens at each stage.

1

Part S Requirements and Planning Conditions

Part S of the Building Regulations sets a baseline: every new dwelling with associated parking must have either a passive cable route (25-32mm conduit with draw wire) or an active 7kW charge point. In practice, local planning authorities frequently go further. Many councils now require an active 7kW charger at every parking space as a planning condition, and some require 22kW capability for larger spaces. USP reviews the specific planning consent and Part S requirements for your scheme before design commences, so the infrastructure meets both the regulatory minimum and any planning obligations.

2

Understanding EV Load Impact on Grid Connections

A single 7kW charger roughly doubles the peak electrical demand of a new-build dwelling. For a 100-plot scheme with one charger per home, the theoretical unmanaged peak demand is 700kW on top of the base domestic load. In practice, DNO diversity modelling and smart charging demand-side response reduce the real coincident peak, but the load assessment must account for EV from the outset to size the grid connection correctly. USP prepares a full diversity-adjusted load model before submitting any application to the DNO or IDNO, ensuring the connection is sized for the actual EV-inclusive demand rather than the base domestic load alone.

3

Infrastructure Options: Houses, Apartments and Future-Proofing

For houses with individual parking spaces, the simplest approach is a dedicated 7kW circuit to each plot, either as a direct charger installation or as a fused spur ready for the future charger. For apartment schemes, individual circuits back to each flat meter are impractical. The standard solution is a feeder pillar in the car park supplying dedicated charging bays with sub-metering so residents are billed for their own consumption. For developments where immediate EV installation is not required but future demand is anticipated, passive ducting (25-32mm conduit with draw wire installed during civils) allows chargers to be added at minimal cost later without breaking ground again.

4

Smart Charging, DNO Notification and G99/G100 Compliance

Smart charging allows the charge rate to be reduced automatically when overall demand is high, significantly reducing coincident peak and the required grid connection capacity. Any EV charger above 3.68kW on a single-phase supply, or above 11kW on a three-phase supply, requires DNO notification under Engineering Recommendation G99 or G100. For larger schemes with multiple chargers, a formal application rather than simple notification may be required. USP manages the full DNO notification and application process, ensures all chargers are G99/G100 compliant, and designs the smart charging system to work within the agreed Maximum Import Capacity.

EV charge points installed in a residential development car park with branded charge point equipment
Proof on the Ground

See it in action

Every EV installation we deliver is DNO-notified, Part S compliant, and smart-charging capable. These are real USP projects, not stock photos.

500+
EV connections delivered
50
5-star Google reviews
10+
Industry accreditations
Key Technical Considerations

Technical Specifications

The critical parameters that govern every residential EV charging installation.

Part S minimum
Passive cable route (25-32mm conduit with draw wire) or active 7kW charge point per parking space associated with a new dwelling.
Typical planning requirement
Active 7kW charger per space. Some authorities require 22kW for larger developments. Check the specific planning consent before design.
Smart charging
Demand-side response capable charger required for G99/G100 compliance above 3.68kW single-phase. Reduces coincident peak and connection capacity requirement.
Apartment metering
Feeder pillar with sub-metering per bay. Allows individual resident billing and avoids landlord / tenant metering complexity.
Passive ducting
25-32mm conduit with draw wire. Installed during civils at marginal extra cost. Allows future active installation without breaking ground.
DNO notification
G99 notification required above 3.68kW single-phase, G100 for multiple units. Formal application may be required for larger schemes.
From Our Sites

Real EV Charging Work

Why Choose USP

What USP Can Do For You

End-to-end EV charging capability from a single NERS-accredited provider.

USP designs EV charging infrastructure from the ground up as part of the multi-utility package, ensuring it is not an afterthought but an integral part of the grid connection from day one.
Full DNO load assessment including EV diversity and smart charging modelling, so your grid connection is correctly sized and not over-engineered at unnecessary cost.
Apartment feeder pillar design with sub-metering, resolving the billing and metering complexity that catches many developers out on multi-occupancy schemes.
Passive ducting installed at marginal cost during the civils programme, future-proofing plots where immediate charger installation is not required by planning.
Full G99/G100 notification and application management, ensuring every charger on the development is DNO-compliant without placing the administrative burden on the developer.
Certified Provider

Fully Accredited & Committed to Safety

Every EV connection we deliver meets the highest industry standards. Worker safety, public safety, environmental responsibility, and project compliance from planning to sign-off.

WaterSafe accredited
WIAPS accredited
LRQA WIRS certified
LRQA NERS certified
LRQA GIRS certified
ISO 9001 certified
Achilles UVDB Silver Plus
Constructionline member
SSIP accredited
Acclaim accredited
What Our Clients Say About Us

Rated 5.0 ★★★★★

50 Google Reviews

Residential EV Charging FAQs

Frequently Asked Questions

Part S, which applies to new dwellings in England from June 2022, requires that every new home with an associated parking space has either a cable route (passive provision) or an active 7kW EV charge point installed. Many local planning authorities go further and require an active 7kW charger at every space as a planning condition, so it is important to check your specific consent before assuming passive ducting will satisfy the requirement.
A single 7kW charger roughly doubles the peak electrical demand of a typical new-build dwelling. For a 100-plot scheme, the theoretical unmanaged peak rises by 700kW. In practice, DNO diversity factors and smart charging demand-side response reduce the actual peak significantly, but the load assessment must account for EV from the outset. USP carries out a full load assessment including EV diversity modelling before submitting any grid connection application.
Apartments cannot easily have individual chargers wired back to each flat meter, so the standard approach is a feeder pillar in the car park with dedicated supplies to each charging bay, metered separately. This allows residents to be billed accurately for their own consumption. USP designs the feeder pillar layout, sub-metering arrangement, and associated cabling as part of the multi-utility package for apartment schemes.
A standard (dumb) charger draws its full rated power continuously whenever a car is plugged in. A smart charger communicates with a demand-side response system, allowing the charge rate to be reduced automatically when overall grid demand is high. Smart charging reduces the coincident peak and can significantly cut the required grid connection capacity. DNO G99 or G100 notification is required for any charger above 3.68kW on a single-phase supply.
EV chargers on new residential developments are typically required by the planning consent itself (as a condition) and do not require a separate application. However, on existing buildings or car parks, permitted development rights for EV chargers are limited. USP advises on planning requirements as part of the design process and can prepare any necessary submissions.
Yes. USP installs gas, water, and electricity connections for residential developments under a single contract, and EV charging infrastructure can be incorporated into the same programme. Combining utilities reduces civils costs, limits disruption to the build programme, and gives you a single point of contact for all utility matters.
Get Started

Need EV Charging Infrastructure
for Your Development?

Tell us about your project and we will send you a free, no-obligation EV charging plan within 24 hours.

100% free, no obligation Response within 24 hours 5.0 from 50 Google reviews

Prefer to talk? Call 024 7542 6505 for immediate service.

Get a Quote